Vineyard Wind Sues GE Vernova, US Monopile Factory Bankrupt
Allen covers EEW American Offshore Structures’ Chapter 11 filing, Vineyard Wind suing GE Vernova for $545 million, Europe’s exit from Korea, and wind project wins in Australia and Canada.
Sign up now for Uptime Tech News, our weekly newsletter on all things wind technology. This episode is sponsored by Weather Guard Lightning Tech. Learn more about Weather Guard’s StrikeTape Wind Turbine LPS retrofit. Follow the show on YouTube, Linkedin and visit Weather Guard on the web. And subscribe to Rosemary’s “Engineering with Rosie” YouTube channel here. Have a question we can answer on the show? Email us!
There is a story unfolding across this industry right now. It is a story of two worlds. One world is closing its doors. The other is throwing them wide open.
Let us start in New Jersey. EEW American Offshore Structures filed for Chapter Eleven bankruptcy on April eighth. This was the first monopile manufacturing facility ever built in the United States. New Jersey Governor Phil Murphy announced a two hundred fifty million dollar investment in the Paulsboro Marine Terminal back in twenty twenty. It was called the largest industrial offshore wind investment in the country at the time. At full buildout… five hundred thousand square feet of production space. More than one hundred monopiles per year. Five hundred workers. They even built the first American-made monopile… for Orsted’s Ocean Wind project. It weighed three million pounds. It measured three hundred feet long.
Then Orsted canceled Ocean Wind One and Two. Then Shell pulled out of Atlantic Shores. Without contracted work… workers disassembled and recycled finished monopiles for scrap. Federal policy shifts removed the pipeline of future projects. A landlord eviction filing followed. And then… Chapter Eleven. That is a two hundred fifty million dollar facility… with nowhere left to go.
Now stay with us. Because just offshore… another American offshore wind story is fighting for its life. Vineyard Wind… the sixty-two turbine project fifteen miles south of Martha’s Vineyard… filed suit in Massachusetts against GE Renewables. GE Vernova says Vineyard Wind owes it three hundred million dollars for work already performed… and it wants to walk away at the end of April. Vineyard Wind says not so fast.
The developer says GE still owes five hundred forty-five million dollars for what it calls inexcusably poor performance after a catastrophic turbine blade collapse in July of twenty twenty-four. Fiberglass blade fragments washed onto Nantucket beaches during peak tourist season. Sixty-eight of seventy-two blades had to be removed and replaced. That set the project back nearly two years. Construction did reach completion in March… making Vineyard Wind the first offshore project to finish under the current administration. But now the only contractor capable of completing the remaining work… wants out. A court hearing was scheduled for Thursday.
And now… look eastward. Something similar is playing out in Korea. European offshore wind companies are exiting the Korean market one by one. Corio Generation, a British firm owned by Macquarie, disbanded its Korean unit and pulled out of joint projects in Busan and Ulsan. Germany’s RWE quit offshore wind projects in Taean and Sinan counties. Vestas postponed its turbine factory in Mokpo… indefinitely. Equinor began reducing its Korean workforce. Shell exited the Korean offshore market entirely in twenty twenty-four.
These companies point to worsening global profitability… and Korean government policies they say favor domestic companies over firms with greater experience. Korea had a target of three gigawatts of offshore wind by twenty thirty. That goal is now in serious doubt.
But here is where the story turns. Not every market is closing its door. Eight thousand miles from New Jersey… in the Sunshine State of Queensland, Australia… the final forty-one turbines just arrived at the Wambo wind project. Cubico Sustainable Investments and Stanwell are building a five hundred six megawatt project on the Darling Downs. Stage One… two hundred fifty-two megawatts… already feeding the Queensland grid. Stage Two deliveries are now complete. Commissioning and full operations are on track for the end of twenty twenty-six.
And up in Ontario, Canada… the province just approved fourteen new wind and solar projects totaling more than thirteen hundred megawatts. The average price… eight point eight cents per kilowatt hour. Compare that to twenty-one point four cents for some proposed nuclear projects… and more than thirty-two cents for certain new reactor designs. Contracts run for twenty years, with all projects online before twenty thirty.
So let us step back. In New Jersey… the first American monopile factory files for bankruptcy. Off Massachusetts… a completed offshore wind farm fights to keep its contractor. In Korea… European developers pack their bags. But in Australia… turbines arrive on schedule. And in Canada… wind power undercuts nuclear at the meter.
The wind energy industry is not in retreat. It is choosing its battlegrounds. And where the conditions are right… the blades are turning.
And now you know… the rest of the story.
That is the state of the wind industry for the 13th of April, twenty twenty-six. Join us for the Uptime Wind Energy Podcast tomorrow.
Renewable Energy
Nordex Outsells Vestas, GE Vernova Rebuilds Wind Team
Weather Guard Lightning Tech

Nordex Outsells Vestas, GE Vernova Rebuilds Wind Team
Nordex closes in on Vestas in onshore orders, GE Vernova rebuilds its wind team, Nexxis buys BladeBug, and wooden blades draw doubts.
The Uptime Wind Energy Podcast is brought to you by Weather Guard Lightning Tech, creators of the StrikeTape Ultra LPS retrofit. Subscribe to Uptime’s Substack newsletter. And check out Rosemary’s “Engineering with Rosie” Youtube channel. Have a question we can answer on the show? Email us!
Renewable Energy
Siemens Gamesa Builds Hornsea Blades, NEMS Invests in Perth
Weather Guard Lightning Tech

Siemens Gamesa Builds Hornsea Blades, NEMS Invests in Perth
Siemens Gamesa starts Hornsea 3 blade production in Hull, Germany approves an Offshore Wind Act amendment, and Nexxis buys BladeBUG.
The Uptime Wind Energy Podcast is brought to you by Weather Guard Lightning Tech, creators of the StrikeTape Ultra LPS retrofit. Subscribe to Uptime’s Substack newsletter. And check out Rosemary’s “Engineering with Rosie” Youtube channel. Have a question we can answer on the show? Email us!
Episode Transcript
Uptime News Flash
September 7, 2026
Happy Monday, everyone. Well, let’s talk about the biggest wind farm on earth. It doesn’t exist yet, but its blades are being built right now. Over in Hull, England, Siemens Gamesa just started making blades for Ørsted’s Hornsea 3 offshore wind farm. That’s two point nine gigawatts, one hundred and ninety-seven turbines. Each blade is longer than a football pitch. Fourteen hundred workers build blades in that factory, turning raw materials into finished product. When complete, Hornsea 3 will power more than three million British homes. It’s the single largest offshore wind farm in the world.
And if we slide over to Germany for a moment, the German cabinet just approved an amendment to the Offshore Wind Act, the WindSeeG. It’s headed to the Bundestag next. The goal? New rules by January first, twenty twenty-seven. But the Offshore Wind Energy Foundation says the draft does not go far enough. Sixteen gigawatts of awarded projects are still waiting on final investment decisions. Sixteen — that’s quite a few. The foundation wants a new way for developers to hand back sites they can’t build, so those sites can be re-tendered quickly under conditions that actually work. Sort of a use-it-or-lose-it approach. That’s the idea.
We’ll head a little further east to India. India ranks fourth in the world for installed wind power, but probably not for long. A government official said this week that India will overtake Germany and become the world’s third-largest wind energy nation by twenty thirty — one hundred seven gigawatts of installed capacity. India added a record six gigawatts last year alone, shattering their previous record of a little over four gigawatts. And twenty-eight more gigawatts are under construction right now. Impressive.
Let’s head down to Western Australia, because a company called National Electric Motor Services, NEMS for short, is building a one million dollar facility in Perth to test and repair wind turbine generators. Right now, Australian wind farm operators ship their broken generators overseas for repairs, and that takes months. NEMS is the only authorized service center for ELIN Motoren in all of Western Australia. This is the fifth project funded through Australia’s Wind Energy Manufacturing Co-investment program. Local repair, faster turnaround, and homegrown capability — that’s all good.
And staying in Australia, Perth-based Nexxis Technology just bought a British robotics company, BladeBUG. BladeBUG is a robot that uses suction cups to crawl across wind turbine blades. Nexxis already has a robot called Magneto that uses electromagnetic adhesion to climb steel structures. If you put the two together, you can inspect almost any surface on a turbine, or about anything else. Add AI and machine vision, and you have robots that can see what human eyes might miss, from places human hands shouldn’t have to reach. It’s safer, faster, and it’s going to be a lot smarter.
One more story before we finish today. Siemens Gamesa has now installed more than 300 recyclable blades in six countries. The secret is a new resin. Unlike conventional resins, this one lets you separate the blade components at end of life, so you can separate the fabric from the resin. Cool stuff. Jonas Pagh Jensen, head of sustainability at Siemens Gamesa, says the technology is ready for full-scale use. And Siemens Gamesa has already installed 36 GreenerTower units — steel towers with 63% lower carbon emissions. So although sustainability may have faded from the headlines, it’s still in tender documents, and it’s showing up more than ever. In Denmark, the Netherlands, and France, buyers are all asking about recyclability and decarbonization before they award contracts.
So what should you be watching this week? Recyclability is no longer a nice-to-have — it’s a must-have, and it’s showing up in tender scoring. If your blades can’t be recycled at end of life, you may not win the contract to begin with. And a lot of supply chains are going local. Australia doesn’t want to ship generators overseas anymore. India is building its own turbine factories. The countries buying wind power want it built at home. For professionals in the wind industry, the competitive edge is shifting — it’s not just who can build the best turbine, it’s who can build it locally, recycle it fully, and inspect it without putting a person in a harness.
Renewable Energy
Climate “Superfund” Will Require Legislation at the Federal Level
Eventually, we will have laws that force companies whose actions are ruining the planet to pay for the remediation that must happen to avert environmental collapse. In the meanwhile, we need to expect the fossil fuel industry to continue its ruthless legal attack such legislation.
Climate “Superfund” Will Require Legislation at the Federal Level
-
Climate Change1 year ago
Guest post: Why China is still building new coal – and when it might stop
-
Greenhouse Gases2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Greenhouse Gases1 year ago
Guest post: Why China is still building new coal – and when it might stop
-
Climate Change2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Renewable Energy11 months agoSending Progressive Philanthropist George Soros to Prison?
-
Climate Change2 years ago
Bill Discounting Climate Change in Florida’s Energy Policy Awaits DeSantis’ Approval
-
Greenhouse Gases1 year ago
嘉宾来稿:探究火山喷发如何影响气候预测
-
Carbon Footprint2 years agoUS SEC’s Climate Disclosure Rules Spur Renewed Interest in Carbon Credits

A judge has ruled that New York State’s climate “superfund,” modeled after laws that provide money to clean up toxic waste, runs counter to federal law and is therefore invalid.