New Report: Additional Congressional Oversight Needed to Ensure Tennessee Valley Authority Delivers Low-cost, Reliable Power for Customers
WASHINGTON, D.C. – A new report released today highlights critical steps Congress can take to improve the Tennessee Valley Authority (TVA’s) transmission planning to make electricity service more affordable, reliable and resilient for customers. Produced by the American Council on Renewable Energy (ACORE) in partnership with the Southern Renewable Energy Association (SREA) and in collaboration with Paul Hastings LLP, the report outlines actionable recommendations to prepare TVA for growing energy demands, more frequent extreme weather events, and develop or purchase the lowest-cost generation.
This report is particularly timely as TVA conducts its legally mandated Integrated Resource Plan (IRP) process, an undertaking that currently does not require inclusion of the transmission expansion options necessary to ensure procurement of the lowest-cost power options. Notably, the TVA service territory experienced rolling blackouts for the first time in its more than 90-year history during Winter Storm Elliott in 2022, when the region’s power supply could not meet demand. An extra gigawatt of transmission ties to other regions could have saved TVA consumers up to $95 million during the storm.
“As the region navigates some of the most significant challenges to the power sector since those that inspired the TVA Act, TVA’s ratepayers would benefit from transmission planning processes consistent with the best practices other grid planners are using across the nation,” said Jonathan Geldof, Senior Government Affairs Manager for ACORE’s Macro Grid Initiative. “It’s encouraging to see Congress and TVA’s Board of Directors already taking steps to improve TVA’s processes and this report offers additional recommendations for ensuring low-cost power in the regions’ future.”
Amid skyrocketing load projections, integrating transmission and generation planning will help ensure reliable, affordable power for TVA’s 10 million customers.
The report, “Recommendations for Reducing Costs and Improving Reliability for Tennessee Valley Authority Customers,” provides various policy interventions for Congress to improve TVA’s transmission planning, including:
- Reforming TVA’s Board
- Reforming TVA’s IRP Process
- Requiring Expanded Interregional Transmission Planning
- Permitting Reform
- Bringing TVA Under Federal Energy Regulatory Commission Jurisdiction
“With increasing challenges to reliability of the TVA system during extreme weather events, like Winter Storm Elliott, and the timely and affordable integration of renewable energy, transmission planning in the largest public power company in the U.S. needs an upgrade,” said Simon Mahan, SREA’s Executive Director. “Outdated processes that are often lacking in transparency for the broader public have been the status quo in TVA for the past 90 years, but this approach will not be sufficient for the future of the organization. This study on improvements to TVA transmission planning provides sound advice on how to confront and overcome these challenges.”
Unlike traditional utilities, TVA’s Board of Directors is the only entity that oversees the IRP process. Congress can help ensure the board is equipped to work in the best interests of ratepayers by providing the directors with technical staff support to better assess TVA’s proposals.
The report details these issues and more, recommending a suite of reform options for Congress to consider.
To download a copy of the report, click here.
###
About ACORE:
For over 20 years, the American Council on Renewable Energy (ACORE) has been the nation’s leading voice on the issues most essential to clean energy expansion. ACORE unites finance, policy, and technology to accelerate the transition to a clean energy economy. For more information, please visit www.acore.org.
Media Contacts:
Dylan Helms
Manager, Communications, ACORE
communications@acore.org
917.971.7852
Ellie Potter
Sr. Public Affairs Manager, Macro Grid Initiative, ACORE
potter@acore.org
202.505.5589
Jamie Moody
Communications Director, SREA
jamie@southernrenewable.org
501.454.1260
The post New Report: Additional Congressional Oversight Needed to Ensure Tennessee Valley Authority Delivers Low-cost, Reliable Power for Customers appeared first on ACORE.
https://acore.org/news/new-report-additional-congressional-oversight-needed-to-ensure-tennessee-valley-authority-delivers-low-cost-reliable-power-for-customers/
Renewable Energy
Vineyard Wind Sues GE Vernova, US Monopile Factory Bankrupt
Weather Guard Lightning Tech

Vineyard Wind Sues GE Vernova, US Monopile Factory Bankrupt
Allen covers EEW American Offshore Structures’ Chapter 11 filing, Vineyard Wind suing GE Vernova for $545 million, Europe’s exit from Korea, and wind project wins in Australia and Canada.
Sign up now for Uptime Tech News, our weekly newsletter on all things wind technology. This episode is sponsored by Weather Guard Lightning Tech. Learn more about Weather Guard’s StrikeTape Wind Turbine LPS retrofit. Follow the show on YouTube, Linkedin and visit Weather Guard on the web. And subscribe to Rosemary’s “Engineering with Rosie” YouTube channel here. Have a question we can answer on the show? Email us!
There is a story unfolding across this industry right now. It is a story of two worlds. One world is closing its doors. The other is throwing them wide open.
Let us start in New Jersey. EEW American Offshore Structures filed for Chapter Eleven bankruptcy on April eighth. This was the first monopile manufacturing facility ever built in the United States. New Jersey Governor Phil Murphy announced a two hundred fifty million dollar investment in the Paulsboro Marine Terminal back in twenty twenty. It was called the largest industrial offshore wind investment in the country at the time. At full buildout… five hundred thousand square feet of production space. More than one hundred monopiles per year. Five hundred workers. They even built the first American-made monopile… for Orsted’s Ocean Wind project. It weighed three million pounds. It measured three hundred feet long.
Then Orsted canceled Ocean Wind One and Two. Then Shell pulled out of Atlantic Shores. Without contracted work… workers disassembled and recycled finished monopiles for scrap. Federal policy shifts removed the pipeline of future projects. A landlord eviction filing followed. And then… Chapter Eleven. That is a two hundred fifty million dollar facility… with nowhere left to go.
Now stay with us. Because just offshore… another American offshore wind story is fighting for its life. Vineyard Wind… the sixty-two turbine project fifteen miles south of Martha’s Vineyard… filed suit in Massachusetts against GE Renewables. GE Vernova says Vineyard Wind owes it three hundred million dollars for work already performed… and it wants to walk away at the end of April. Vineyard Wind says not so fast.
The developer says GE still owes five hundred forty-five million dollars for what it calls inexcusably poor performance after a catastrophic turbine blade collapse in July of twenty twenty-four. Fiberglass blade fragments washed onto Nantucket beaches during peak tourist season. Sixty-eight of seventy-two blades had to be removed and replaced. That set the project back nearly two years. Construction did reach completion in March… making Vineyard Wind the first offshore project to finish under the current administration. But now the only contractor capable of completing the remaining work… wants out. A court hearing was scheduled for Thursday.
And now… look eastward. Something similar is playing out in Korea. European offshore wind companies are exiting the Korean market one by one. Corio Generation, a British firm owned by Macquarie, disbanded its Korean unit and pulled out of joint projects in Busan and Ulsan. Germany’s RWE quit offshore wind projects in Taean and Sinan counties. Vestas postponed its turbine factory in Mokpo… indefinitely. Equinor began reducing its Korean workforce. Shell exited the Korean offshore market entirely in twenty twenty-four.
These companies point to worsening global profitability… and Korean government policies they say favor domestic companies over firms with greater experience. Korea had a target of three gigawatts of offshore wind by twenty thirty. That goal is now in serious doubt.
But here is where the story turns. Not every market is closing its door. Eight thousand miles from New Jersey… in the Sunshine State of Queensland, Australia… the final forty-one turbines just arrived at the Wambo wind project. Cubico Sustainable Investments and Stanwell are building a five hundred six megawatt project on the Darling Downs. Stage One… two hundred fifty-two megawatts… already feeding the Queensland grid. Stage Two deliveries are now complete. Commissioning and full operations are on track for the end of twenty twenty-six.
And up in Ontario, Canada… the province just approved fourteen new wind and solar projects totaling more than thirteen hundred megawatts. The average price… eight point eight cents per kilowatt hour. Compare that to twenty-one point four cents for some proposed nuclear projects… and more than thirty-two cents for certain new reactor designs. Contracts run for twenty years, with all projects online before twenty thirty.
So let us step back. In New Jersey… the first American monopile factory files for bankruptcy. Off Massachusetts… a completed offshore wind farm fights to keep its contractor. In Korea… European developers pack their bags. But in Australia… turbines arrive on schedule. And in Canada… wind power undercuts nuclear at the meter.
The wind energy industry is not in retreat. It is choosing its battlegrounds. And where the conditions are right… the blades are turning.
And now you know… the rest of the story.
That is the state of the wind industry for the 13th of April, twenty twenty-six. Join us for the Uptime Wind Energy Podcast tomorrow.
Renewable Energy
Criticizing Trump
Did Jennifer Lawrence really say this? I hope not, because it’s complete stupidity.
People who didn’t criticize Hitler, Mussolini, or the dozens of other fascist dictators as they were rising to power merely ushered them into a position in which they could destroy the lives of millions of innocent lives.
Renewable Energy
Birthright Citizenship
The author of the meme at left writes, “We’re the only ones.”
This is completely incorrect, not that you care about facts and truth. Over 30 countries, primarily in the Americas, offer unconditional birthright citizenship, granting citizenship to almost anyone born within their territory, regardless of their parents’ status.
-
Climate Change8 months ago
Guest post: Why China is still building new coal – and when it might stop
-
Greenhouse Gases8 months ago
Guest post: Why China is still building new coal – and when it might stop
-
Greenhouse Gases2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Climate Change2 years ago
Bill Discounting Climate Change in Florida’s Energy Policy Awaits DeSantis’ Approval
-
Climate Change2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Climate Change Videos2 years ago
The toxic gas flares fuelling Nigeria’s climate change – BBC News
-
Renewable Energy6 months agoSending Progressive Philanthropist George Soros to Prison?
-
Carbon Footprint2 years agoUS SEC’s Climate Disclosure Rules Spur Renewed Interest in Carbon Credits
