The Federal Energy Regulatory Commission (FERC) has granted a waiver to PJM Interconnection LLC, allowing a 210-MW solar project in Indiana to relocate to a different location on the same transmission line. Despite objections from PJM and Commissioner Mark Christie, the waiver was approved, enabling the Rush Solar Project II to proceed with its plans.
Originally intended for Rush County, the solar project faced setbacks. The county, along with neighboring Fayette County, imposed moratoriums on solar permit applications until at least January 2025. In response, Rush Solar sought permission to move the project to Dearborn County under alternate site provisions in PJM’s grid connection study process.
Local Land Concerns and Regulatory Hurdles
The challenges encountered by Rush Solar highlight local land concerns in states like Indiana. This is where renewable energy policy is not uniformly addressed at the state level.
Brian Flory of Solar United Neighbors noted the diverse county policies regarding solar power, with some counties welcoming it while others oppose it.
Indiana’s agricultural landscape, with a significant portion of corn production going to ethanol, adds complexity to the debate. Concerns over land use changes, particularly the conversion of farmland to solar farms, have led to resistance from residents.
PJM objected to the waiver, citing conflicts with interconnection queue reforms and questioning Rush Solar’s good faith in seeking the waiver. PJM argued that granting the waiver could set a precedent for circumventing site control requirements. And it may also delay grid studies for other projects in the interconnect queue.
Despite these objections, FERC approved the waiver, allowing Rush Solar to proceed with its solar project in Dearborn County. The decision underscores the complexities and challenges of renewable energy development at the local level amidst evolving regulatory landscapes.
Just for April, several states involving large renewable developers have made significant strides in advancing massive solar projects. Virginia, Illinois, and Texas have approved solar projects, boosting their renewable energy supply.
FERC’s Decision and Dissenting Voice
In an April 5 order, the majority of the FERC determined that Rush Solar met the criteria for a waiver, despite objections from PJM Interconnection LLC. The commission concluded that Rush Solar acted in good faith, engaged with local officials, and pursued alternative sites only after the county moratoriums were imposed.
FERC stated that the waiver was limited in scope. It allows Rush Solar to change the project site to a non-adjacent alternate site while remaining subject to other site control verification requirements.
The commission rejected PJM’s concern that granting the waiver would encourage circumvention of site control requirements, noting that Rush Solar had originally intended to locate the project in Rush County.
However, Commissioner Mark Christie dissented, arguing that the majority disregarded the more stringent site control requirements approved for PJM in November 2022. He expressed concern that the order failed to adequately justify granting the waiver.
Moreover, it could undermine efforts to reduce speculative projects and grid connection study delays.
Corporate Support and Community Solar Growth
The corporate world in the U.S. is also keen on supporting the unstoppable rise of solar power.
A White House report reveals plans for the announcement of over 100 gigawatts (GW) of solar module manufacturing capacity. This capacity could potentially produce enough solar panels to power approximately 10% of homes in the U.S., amounting to over $13 billion in investments.

Apart from Amazon which is leading the pack of renewable giants, startups are also making waves in this revolution.
Boston-based Nexamp Inc. has secured $520 million in funding to bolster its national portfolio of community solar projects. Led by Manulife Investment Management Ltd., the capital raise also saw participation from existing investors Diamond Generating Corp. and Generate Capital PBC.
Community solar projects offer consumers the benefits of onsite solar generation without the complexities of rooftop solar. This enables them to earn credits on their power bills by owning or subscribing to a portion of a community solar farm.
This electricity model is gaining traction in the US, with 6.5 GW of community solar arrays already installed, according to the Solar Energy Industries Association. The association predicts an additional 6 GW of capacity will be added to the community solar market over the next five years.
Nexamp’s latest funding round highlights the crucial role of community solar in providing clean and affordable energy solutions to all Americans, remarked CEO Zaid Ashai.
Nexamp currently serves over 80,000 customers and manages a 1.5-GW portfolio, including projects in progress. The company intends to expand its capacity by multiple gigawatts in the coming years, aiming to provide power to over a million customers.
The post FERC Grants Waiver for Solar Project Amidst Local Resistance appeared first on Carbon Credits.
Carbon Footprint
Insetting vs Offsetting: Which Actually Counts Toward Your Scope 3 Targets
The accounting differences that decide whether your nature investment shows up in inventory, in BVCM, or nowhere at all.
The question reaches a procurement team about three weeks before the next sustainability committee meeting. Someone has read about insetting. Someone else has just signed off on an offset purchase. The CSO wants to know if the two are interchangeable. The answer is no, and the GHG Protocol Land Sector and Removals Standard is the reason why.
This article walks through what each term means at audit-grade specificity, what the standards actually say about how each gets counted, and how to decide which tool fits which target. The insetting vs offsetting question is one of the most-searched in corporate climate strategy, and one of the most poorly answered. By the end of this piece, you should be able to brief a committee on the difference without notes.
The two definitions, in plain English
Offsetting means buying carbon credits generated outside your value chain and retiring them against your residual emissions. The reduction happens somewhere else, financed by you, and the credit is the receipt.
Insetting means investing in emission reductions or removals inside your own value chain, typically with suppliers, where the reduction is directly linked to the products and services you buy. The reduction happens inside the boundary of your Scope 3 inventory, and the accounting treatment is fundamentally different.
The shorthand from the University of Oxford’s Nature-based Insetting Initiative is useful: insetting is what you do with the supply chain you have; offsetting is what you do with the supply chain you do not have.
What the GHG Protocol Land Sector Standard actually says
The GHG Protocol Land Sector and Removals Standard, finalised in 2024 after a multi-year pilot, sets the rules for how land-based emission reductions and removals enter corporate inventories. The Standard distinguishes between inventory accounting (Scope 1, 2, and 3) and project or intervention accounting (a separate methodology for crediting).
For insetting, the practical implication is that supplier-level interventions, when properly measured and attributed, can reduce your Scope 3 category 1 (purchased goods and services) emissions in your inventory. The reduction is not a credit retired against the inventory; it is a lower inventory number, period.
For offsetting, the credit is retired separately. It can be reported as a contribution toward a net-zero claim under the SBTi Beyond Value Chain Mitigation framework or as part of a VCMI Carbon Integrity claim, but it does not lower the inventory number.
A practical consequence: if your Science Based Target requires a 50% absolute reduction in Scope 3 emissions by 2030, insetting moves you toward the target. Offsetting does not. This single point of difference reshapes the procurement decision.
When insetting counts toward Scope 3 (and when it does not)
Insetting counts toward Scope 3 only when several conditions are met:
- The intervention must occur with an entity in your value chain.
- The emissions reduction or removal must be measured against a defensible baseline.
- The reduction must be attributed to your share of that supplier’s output, not double-counted with other buyers.
- It must follow the inventory accounting rules in the GHG Protocol Land Sector Standard, not the project accounting rules used to generate credits.
The most common failure mode is double counting. If your supplier sells the same reduction as a credit on the voluntary market and also reports it to you as a Scope 3 reduction, the math breaks. The Standard requires you to address this risk, typically by purchasing and retiring the supplier-issued credit as part of your inventory or by contractual provisions that prevent the supplier from selling the reduction twice.
When insetting does not count toward Scope 3: when the intervention sits with a supplier you do not buy from, when the baseline is not defensible, when the attribution is unclear, or when the documentation does not survive audit. Those cases default to Beyond Value Chain Mitigation, which is still useful but operates on a different ledger.
The procurement and supplier engagement question
Insetting is harder than offsetting. That is the unfashionable truth most buyers eventually confront. Offsetting is a transaction; insetting is a relationship.
To run an insetting program, you need supplier mapping precise enough to know which farms or facilities sit at which Scope 3 boundary. You need an engagement model that gets suppliers to participate, which usually requires multi-year commitments and shared economics. You need an MRV architecture that measures the right things and produces audit-ready documentation. And you need a contractual structure that prevents double counting and protects both sides.
The trade-off you receive in return is significant. Reductions count against your inventory rather than your residual. Supplier relationships deepen, which protects sourcing continuity. Yield and quality improvements often follow regenerative interventions, which reduces your input cost over time. And the regulatory file, under CSRD, CSDDD, EUDR, and the SBTi FLAG Guidance, is materially stronger.
Choosing the right tool for the right target
A practical decision rule. If your target is a science-based Scope 3 reduction and you operate in a FLAG sector or source FLAG commodities, insetting is the structurally correct tool. If your target is a net-zero claim that includes neutralising hard-to-abate residual emissions outside your value chain, BVCM via high-integrity offsets is the structurally correct tool. Most companies with material Scope 3 exposure need both, in different proportions, sequenced over time.
The sequencing matters. Insetting takes longer to stand up but produces a permanent reduction in the inventory. Offsetting can be transacted faster but does not change the inventory and now sits under tighter claim restrictions. Treat them as complementary tools with different jobs, not as substitutes. The Accountability Framework Initiative and the IUCN Global Standard for Nature-based Solutions both provide useful guardrails for the insetting side, with biodiversity, human rights, and benefit-sharing requirements that go beyond carbon math.
If you are mapping a Scope 3 reduction roadmap and need to scope which interventions count toward your inventory versus which sit in Beyond Value Chain Mitigation, the carbon and sustainability experts at Carbon Credit Capital can help you structure a nature-based supply chain investment program that fits your FLAG exposure, your target architecture, and your audit horizon. Schedule a consultation.
Carbon Footprint
Net zero needs nature: a carbon credit guide
Net zero is often described as a balancing act: cut what you can, account for the rest, and reach zero on the ledger. That framing is useful, but it leaves something out. It treats every tonne of carbon as interchangeable and every route to zero as equally sound, while the science tells a more specific story.
![]()
Carbon Footprint
Deforestation in Malawi: causes and solutions
Malawi has lost a striking share of its forests over the past three decades. Woodlands that once covered well over a third of the country now cover less than a quarter, and the pressure on what remains is increasing. Behind those figures sit two practical questions: what is driving the loss, and what reverses it?
![]()
-
Climate Change1 year ago
Guest post: Why China is still building new coal – and when it might stop
-
Greenhouse Gases1 year ago
Guest post: Why China is still building new coal – and when it might stop
-
Greenhouse Gases2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Climate Change2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Climate Change2 years ago
Bill Discounting Climate Change in Florida’s Energy Policy Awaits DeSantis’ Approval
-
Renewable Energy10 months agoSending Progressive Philanthropist George Soros to Prison?
-
Greenhouse Gases1 year ago
嘉宾来稿:探究火山喷发如何影响气候预测
-
Carbon Footprint2 years agoUS SEC’s Climate Disclosure Rules Spur Renewed Interest in Carbon Credits

