The UK government has set out an “action plan” for reaching its target of clean power by 2030, which it describes as “the most ambitious reforms to our energy system in generations”.

The plan outlines how the government hopes to “make Britain a clean energy superpower to cut bills, create jobs and deliver security with cheaper, zero-carbon electricity by 2030”.

This was one of five “missions” in the Labour manifesto, on which the government was elected with a landslide majority in July.

Following independent advice from the National Energy System Operator (NESO), the government is aiming for clean power to meet 100% of electricity demand by 2030, with at least 95% of electricity generation coming from low-carbon sources and no more than 5% from unabated gas.

The 136-page plan sees wind and solar – in particular offshore wind – becoming the backbone of the British electricity system. It says record amounts of new renewable capacity will need to be delivered, alongside reforms to the planning process and major grid enhancements.

While delivering all this would be a huge undertaking, the plan says it could unlock extra investments worth £40bn a year out to 2030, delivering “reindustrialisation”, jobs and lower bills.

Here, Carbon Brief explains the background to the clean power 2030 target, initial steps already taken by the government, the proposals in the new action plan and what comes next.

Where the clean power 2030 target comes from

The Labour party fought the 2024 UK election campaign on a manifesto pledging to “make Britain a clean energy superpower…with cheaper, zero-carbon electricity by 2030”.

This was an advance on the previous Conservative government’s 2021 pledge to “fully decarbonise” the power system by 2035.

Both parties had identified the need for clean power in order to help decarbonise the rest of the UK economy, as heat and transport are increasingly electrified with heat pumps and electric vehicles.

However, the Labour party has explicitly tied its clean power “mission” not just to the UK’s climate goals, but to energy security and bills in the wake of the global energy crisis, as well as jobs.

In a press statement launching the report, secretary of state for energy and climate change Ed Miliband says:

“A new era of clean electricity for our country offers a positive vision of Britain’s future with energy security, lower bills, good jobs and climate action. This can only happen with big, bold change and that is why the government is embarking on the most ambitious reforms to our energy system in generations. ”

Just after taking office at the start of July 2024, Miliband reiterated his commitment to the clean power 2030 target when setting out his priorities for government.

He then appointed Chris Stark, the former chief executive of the Climate Change Committee, to head up a new “mission control” function within government, as well as informally asking NESO for independent advice on how to reach the clean power 2030 target.

(NESO was created as part of the Energy Act 2023, having already been hived off from National Grid. It was officially launched on 1 October 2024 as a new independent organisation responsible for planning the entire energy system in Britain, including operating the electricity network and offering “expert advice to the energy sector’s decision makers”.)

Speaking to UK Energy Research Centre (UKERC) director Prof Rob Gross on the Talking Energy podcast, NESO chief economist Mike Thompson said the body had begun working on its advice to government in July 2024, soon after the election result became clear.

The government had then formally requested NESO’s guidance in an August 2024 letter, which asked for “practical advice on achieving clean power by 2030”.

It asked for different pathways to reach this goal, as well as key requirements for electricity grids, high-level analysis of costs and benefits, and suggested actions to get on track.

The NESO advice, published on 5 November 2024, said the 2030 target was “achievable…without increasing costs” and that it would insulate the UK from “volatile international gas prices”.

A key element of the NESO advice was to offer a working definition of clean power by 2030.

It adopted a definition with two parts. It said clean power should cover 100% of electricity demand by 2030, in a year with average weather conditions. In addition, it said at least 95% of the electricity generated within the country’s borders should come from low-carbon sources, with up to 5% coming from unabated gas. This means the country would become a net electricity exporter.

(The national electricity grid – and the clean power 2030 target – technically only covers the island of Great Britain, whereas Northern Ireland is part of the separate all-Ireland network.)

Thompson explained on the Talking Energy podcast:

“We think that there should be enough clean power to cover all of GB demand over the year…But of course, a lot of that generation is coming from wind power, from solar, and you can’t control when it is outputting…So we adopted this definition that actually you cover all of demand [with clean power], but you would also allow up to no more than 5% of generation to come from unabated gas.”

The government formally adopted the NESO definition of clean power when prime minister Keir Starmer announced his milestones for delivering a “decade of national renewal”.

This definition, for clean power to meet 100% of demand in 2030 but only 95% of generation, was widely reported as a “watering down” of Labour’s manifesto pledge. A spokesperson for the Department of Energy Security and Net Zero said this was “categorically untrue”.

Labour’s manifesto had not defined its clean power by 2030 target and had made clear reference to a “strategic reserve of gas power”.

An earlier Labour policy document had said that the country would “run on 100% clean…power”, which is consistent with the government’s target for clean power to meet 100% of demand.

Back to top

What clean power 2030 will look like

The government’s action plan accepts the NESO advice as its starting point.

While NESO offered two different pathways to clean power in 2030, they share many of the same features, with wind and solar making up the largest share of electricity in both cases.

In 2023, fossil fuels made up a third of electricity generation in the country, with wind and solar making up another third, and the remainder coming from nuclear, biomass and imports.

By 2030, if the clean power target is met, unabated fossil fuels would make up less than 5% of generation, with wind and solar making up around 80% of the mix, as shown in the figure below.

Offshore wind would form the backbone of the GB electricity mix in 2030, meeting around half of demand under either the NESO “new dispatch” scenario or under “further flex and renewables”.

Offshore wind will form backbone of Britain's clean power 2030 target
Electricity generation by source on the GB grid in 2023 and 2030, terawatt hours (TWh), under two different NESO pathways to clean power. Low carbon dispatchable power includes gas with carbon capture and storage, hydrogen and biomass. Other renewables includes hydro and marine power. Other fossil includes coal, oil and diesel. Source: Clean Power 2030 Action Plan.

The difference between the two NESO pathways lies in the way that they manage gaps in the output of variable wind and solar power.

The “new dispatch” pathway relies more on low-carbon “dispatchable” power, meaning capacity that can be turned on and off at will. This includes gas-fired power stations fitted with carbon capture and storage (CCS), or turbines that burn low-carbon hydrogen fuel.

The “further flex and renewables” pathway relies on larger amounts of wind and solar capacity, coupled with a more flexible grid and higher levels of battery or long-duration energy storage.

The government’s action plan targets a range of clean power capacity by 2030 that would leave the door open to pursuing either of these scenarios, shown in the table below.

Crucially, the plan relies on keeping almost all of the country’s existing gas-fired power stations open for the rest of the decade, to help bridge those gaps in wind and solar output, until alternative low-carbon sources of flexibility become more widely available.

Thompson told the Talking Energy podcast:

“You keep something like a fleet around the size of the current gas fleet open [in 2030], but it would operate much, much less.”

While the existing gas fleet remains in place, the government will need to rapidly expand the amount of clean power capacity available to meet the 2030 target.

The action plan says the long timelines for new offshore wind projects mean there will only be time to bring forward schemes that are already or at least part-way through the planning process.

It also means that the next two “contracts for difference” (CfD) auctions, due to be held in 2025 and 2026, will need to secure the bulk of the offshore wind capacity required for 2030.

The UK currently has 15 gigawatts (GW) of offshore wind capacity, with another 16GW under construction or firmly committed. To meet the level required for clean power by 2030, the plan says that this would need to expand by at least another 12GW by 2030.

Similarly, at least an additional 8GW of onshore wind and 22GW of solar would be needed.

The Financial Times quoted a “government figure” saying that next year’s auction will need to be “huge” and the biggest ever for the country:

“When you think about the long lead times for a project like an offshore wind farm it makes sense to get going with the CfDs now and throw the book at this with a huge auction round as soon as possible, probably next year…It would be the biggest we’ve seen so far.”

In addition to building that new capacity, the plan relies on significantly enhancing the electricity transmission grid that sends power around the country, reforming the planning system so that new infrastructure can be built and ensuring the supply chains and workers are in place to deliver.

In a foreword to the action plan, Stark says the wider economic benefits of meeting the target are a “prize” worth around £40bn in investment every year until 2030.

The plan describes this as “once-in-a-generation levels of energy investment” that will “spread…the economic benefits of clean energy investment throughout the UK”. It adds:

“These investments will protect electricity consumers from volatile gas prices and be the foundation of a UK energy system that can bring down consumer bills for good. Every choice we make will be scrutinised to maximise the impact it can have in reducing consumer bills.”

The plan says that the clean power plan will “provide…the foundation to build an energy system that can bring down bills for households and businesses for good.” It adds:

“In their advice, NESO set out their analysis of potential impacts of delivering clean power on electricity costs in 2030. This indicated it could be delivered with similar costs to today, with scope for lower electricity costs and bills by 2030 as wider changes are taken into account.”

Ahead of the general election, Labour had promised that its clean power plan would cut energy bills by up to £300. The opposition Conservatives have disputed this.

On the question of how it would be possible to reduce bills while building large amounts of new infrastructure, UKERC’s Gross explained on the Talking Energy podcast that instead of spending large amounts on imported fossil fuels that are burned to generate electricity, billpayers would be investing in new clean power capacity, which would be paid back over many years.

Back to top

How the government plans to reach clean power 2030

Achieving the clean power 2030 target would be a major undertaking. The government’s action plan sets out its approach to delivering this across a series of key areas.

Actions include reforming and expanding the government’s auctions for new clean power capacity, significantly expanding the country’s electricity grid and speeding up the process of connecting new projects, changing the planning system so that all this new infrastructure can be consented and built, and ensuring a supply chain with skilled workers is in place to deliver it.

Grid enhancement

The action plan outlines steps to expand and improve the electricity grid, saying that a failure to strengthen it "risks holding back our energy security, economic growth and other important infrastructure with lengthy delays”.

For example, it notes that, if no action is taken to address the annual “constraint costs” caused when networks are unable to carry all of the clean power being generated to where it is needed, then those costs are projected to increase from the “already high level” of £2bn per year in 2022 to around £8bn per year (or £80 per household) by the late 2020s.

An “unprecedented expansion” is therefore needed to deliver decarbonisation, energy security and affordability, with around twice as much new transmission infrastructure needed by 2030 as has been delivered in the past decade.

To enable this, the plan sets out several key actions, including reforming the connections process, reforming regulations, improving planning and consenting, and engaging with communities.

In the last five years, the grid “connection queue” of projects waiting to hook up to the electricity network has grown tenfold. Many of the projects within the queue are speculative or do not necessarily have the funding or planning permissions to progress, the action plan notes.

It says this means that fundamental reform is needed. Work has already begun on this. For example, in November the government, together with energy regulator Ofgem, outlined a series of changes in a joint letter that would fast-track renewable, clean power and storage projects.

The action plan includes further reform to the current “first come, first served” process for the queue. The government says it will go beyond previous plans to simply remove slow or stalled projects from the queue and prioritise readiness alone.

It will now also consider technological and locational factors, remove unviable projects, re-order the queue and accelerate connection timescales, the action plan states.

In a foreword to the plan, Miliband says:

“Ultimately, we need to move fast and build things to deliver the once-in-a-generation upgrade of our energy infrastructure Britain needs.”

Following consultations with Ofgem, NESO and network companies, there are now detailed methodologies for filtering the queue and prioritising connections for strategically important plans.

These changes will take into account recommendations from both electricity networks commissioner Nick Winser’s report in 2023 – which set out recommendations to halve the connection times of projects – and NESO’s Clean Power 2030 advice, which confirmed the need for 80 new transmission grid projects to be built, if the target is to be achieved.

Additionally, the action plan notes that, wherever renewable projects can be connected to the lower-voltage local distribution systems, instead of the high-voltage national transmission grid – known as the motorways of the electricity network – this should be encouraged.

(Projects that have secured a CfD or “capacity market” contract, “nationally significant” projects and others that are considered well advanced will be included in the reformed connections queue, according to the plan.)

Beyond the connections queue, the action plan sets out regulatory reforms to support clean power by 2030. This includes amending the Strategy and Policy Statement, wherein the government’s strategic priorities for energy policy are outlined, to ensure that 2030 clean power and decarbonisation more broadly are weighted in decision making.

The government will also work with Ofgem to explore the appropriateness of tightening incentives and penalties for network operators, for the delivery of strategically important infrastructure.

To accelerate the build out of both transmission and distribution networks required for the 2030 target, planning system changes will be required. (See: Planning reforms.)

Currently, it can take between two to four years to gain land rights in England and Wales, which can “lead to unnecessary delays”, the action plan notes.

Electricity pylon cables, Kent, UK. Credit: RichardBakerWork / Alamy Stock Photo.
Electricity pylon cables, Kent, UK. Credit: RichardBakerWork / Alamy Stock Photo.

To address these processes, the action plan says that planning consent exemptions will be expanded to include low-voltage connections and upgrades.

There are also further opportunities to provide flexibilities on the consenting of electricity substations, it adds.

The final core part of action on the grid, outlined in the plan, focuses on community engagement, as “this government believes that it is a vital principle that communities that host clean energy infrastructure should benefit from it”.

This will include publishing voluntary guidance to increase the amount and consistency of community benefit funds from transmissions networks. There will also be support for the launch of a public communications campaign around grid expansion, the plan says.

Back to top

Planning reforms

Since the election in July, the Labour government has taken several steps to help transition the electricity system towards net-zero.

This includes lifting the de-facto ban on onshore wind in England, which had been in place since 2015, within weeks of taking office.

Labour also approved three large solar farms in its first few weeks in government. In total, these sites – Gate Burton in Lincolnshire, Mallard Pass in Lincolnshire and Sunnica in Suffolk and Cambridgeshire – have a capacity of over 1.3GW.

Given their size, all three solar sites are considered nationally significant infrastructure projects (NSIPs), and as such require a development consent order from the energy secretary, as opposed to planning permission from the local planning authority.

One day before the action plan was released, the government published its response to a consultation on proposed changes to the National Planning Policy Framework (NPPF).

This includes plans to bring onshore wind back under the NSIP regime, in line with other types of major infrastructure. It also intends to raise the threshold above which onshore wind and solar projects will need central government NSIP consent to 100 megawatts (MW).

The government is planning to introduce legislation in the spring of 2025 to bring in these changes.

The action plan builds on these changes in an effort to improve the planning process.

It states that the planning system is “not working at the pace required” to meet the 2030 target and that this “urgent need for change” necessitates “a wide-ranging reform programme”.

To enable clean power by 2030, most new transmission grid and offshore wind projects will need all relevant planning permissions to be in place by 2026, the report notes.

While onshore wind, solar and battery energy storage projects have shorter construction timelines, they will still likely need to have received planning consent by 2028.

The report states that the government has identified pathways for delivery for “firm” generation – such as nuclear – as well as for sources of low-carbon flexibility, but does not give a date by which they must be consented.

Other changes outlined in the report include equipping organisations such as the Planning Inspectorate, statutory consultees such as the Environment Agency, local planning authorities and government consenting teams, with the “tools they need” to make decisions faster.

The report highlights that, in 2023-24, more than 60% of delayed responses to planning applications from the Environment Agency were due to resourcing constraints, and for nature regulator Natural England it was more than 80%.

It promises changes including boosting local planning capacity, expanding cost-recovery mechanisms – which see developers pay for the work needed to give them planning consent – and longer-term reforms. In particular, the changes will allow them to “better flex and prioritise their resources” so that “mission-critical projects” can be processed faster, it says.

The action plan includes updating “national policy statements” (NPSs) for energy and planning policy guidance in 2025, along with the changes to the NPPF already announced.

A programme of legislative reform will be undertaken by the government, including through the Planning and Infrastructure Bill, which will be brought forward next year. This will include NPSs being updated every five years, through a “quicker and easier process”.

Further reforms to the NSIP planning system in England and Wales will be undertaken, as well as changes to infrastructure consenting in Scotland.

(There is executive devolution in Scotland with regards to the infrastructure planning system, however under the Electricity Act, reserved to Westminster, the UK government will be able to bring in changes to deliver a “streamlined and efficient framework”, the plan says.)

The report highlights the importance of a coordinated approach to planning and notes that, to support this, NESO will deliver a “strategic spatial energy plan” in 2026, setting out a long-term approach to planning to deliver net-zero by 2050.

Under the NSIP process, the government will undertake a review of the lawfulness of challenges to development consent for major infrastructure. While judicial review is a “constitutionally important mechanism”, the action plan notes, most are unsuccessful and can take many years, significantly delaying new infrastructure and increasing costs to consumers.

As such, the plan includes a commitment to reform the judicial review process for NSIPs, following the Banner report on why such legal challenges arise.

Additional actions announced within the plan include changes to ensure communities can directly benefit from the clean energy infrastructure they host.

It notes that locally-consented energy infrastructure can take up to 12 months to receive a decision on a planning application, despite a four-month limit on projects that require an environmental impact assessment

Finally, the plan says that, by delivering a “marine recovery fund” for offshore wind, as well as using development to fund nature recovery, the government will look to use the action plan to protect nature and ensure that it is embedded in the transition to clean power by 2030.

Back to top

Renewable energy auctions

The action plan announces further changes to the CfD support scheme for new renewable energy.

This follows action by the current government earlier in the year to bolster the sixth CfD auction, including increasing its budget by over 50% from the level set in March under the previous Conservative government to £1.56bn.

(The previous fifth auction, held in 2023, had not secured any new offshore wind.)

This year’s sixth auction contracted more than 130 new wind, solar and tidal energy projects, amounting to 9.6GW of capacity. Still, some cautioned at the time that a “big step-up” would still be required if the power sector is to be decarbonised by the end of the decade.

The government is introducing a number of changes to the CfDs ahead of the seventh auction, due to be held in 2025. This includes allowing onshore wind farms that are “repowering” – meaning replacing old turbines as they retire with newer models – an extension to the “phasing” process for floating offshore wind and streamlining the appeals process to take place ahead of the auction.

There is currently around 31GW of offshore wind built, under construction or contracted. However, this needs to rise to 43-50GW in 2030. (See: What clean power 2030 will look like).

The government will therefore aim to secure at least 12GW of new projects over the next two allocation rounds. To enable this, the action plan sets out further reform to the CfD process.

Changes will include a relaxation of the CfD eligibility criteria for fixed-bottom offshore wind projects to allow projects to bid even if they have not obtained full planning consent.

To avoid a repeat of the fifth auction, there will also be changes to the information the secretary of state uses to inform the final budget for fixed-bottom offshore wind.

There will also be a review of auction parameters, following “industry concerns” around the way the notional “budget” of each round is calculated.

(The “budget” for each auction round is an artificial construct, set by the government and designed to limit the impact of CfDs on consumer bills. Any support for CfD projects is paid for by billpayers rather than from government budgets. Moreover, a larger “budget” may not translate into higher bills, because CfD projects also push down wholesale electricity prices.)

Specifically, the government will look at the “reference price” against which each new CfD scheme is valued. Recent auction rounds have used very low reference prices, which inflate the notional budget impact of new projects, even if they are likely to lower consumer costs.

The government is also considering changes to the CfD contract terms to give longer market security, once the contracts are awarded. This could see the length of the contracts increased from the current 15-year standard term.

Consultations will take place in early 2025, ahead of the seventh allocation round, with a view to implementing them in the summer of 2025.

Beyond the CfD reforms, the action plan includes a number of commitments to improve renewable energy project delivery. These include facilitating greater coordination between wind turbines, civil aviation and defence infrastructure.

Further detail on Great British Energy’s (GBE) project development is included, including promises that the state-owned energy company – a core part of the Labour manifesto – will align its projects on private land with NESOs location suggestions, and develop further projects on public land.

The action plan states that GBE will provide support to deliver the Local Power Plan, to put “local authorities and communities at the heart of restructuring our energy economy”. Additional work will be done to support the deployment of rooftop solar, assess the potential of solar “canopies” on outdoor carparks and support programmes such as the Warm Homes Local Grant.

First introduced in 2002, the UK-wide renewables obligation (RO) scheme currently supports around 30% of the UK’s electricity supply. From 2027, it will start to come to an end, with around 9GW of capacity reaching the end of the subsidy by December 2030.

The action plan commits the government to conduct further analysis to inform the possible policy options needed to manage the risk that RO-supported projects might stop operating.

For the work being undertaken on renewables and nuclear, the action plan includes a list of key upcoming milestones, including:

  • Spring 2025: Solar Roadmap and the Onshore Wind Industry Taskforce report.
  • Early 2025: Consultation on relevant reforms to the CfD scheme.
  • “In due course”: Consultation response on the Future Homes and Buildings Standards.
  • After the spending review: Further details on the Warm Homes Plan.
  • In 2025: A call for evidence on the potential to drive solar canopies on carparks.
  • “In due course”: Consultation response on transitional support for large-scale biomass.

Back to top

Flexibility and ‘dispatchable’ clean power

Beyond renewables, the plan includes a number of actions to reform the electricity market to support energy security, through flexibility and “dispatchable” power.

As with the other core areas, the government has taken a number of actions in its first six months to support this, including signing the contracts for the first gas CCS project in the UK.

French utility firm EDF has also announced plans to keep four existing nuclear power stations open for longer, meaning 4.6GW of nuclear capacity will remain on the grid in 2030.

The action plan includes support for investor certainty through wholesale electricity market reforms, reforming the capacity market and accelerating reforms to the balancing markets through which supply and demand are matched in real time, which it says will help unlock consumer-led flexibility. It notes:

“While the state must play a role as system architect, markets are, and will remain, central to the development, delivery, and operation of the power system.”

The action plan promises to set a clear “direction of travel” for wholesale market reform. As part of this, it is continuing to conduct further analysis as part of the long-running review of electricity market arrangements (REMA), which began in 2022 under the previous government. The action plan says that its work so far has made clear that “no change” is not an option.

The government says it will conclude the REMA process by “around mid-2025”, including whether to bring in “zonal pricing” or whether electricity prices will continue to be set at national level.

Currently, Britain uses a national pricing system whereby generators are paid the same regardless of where they are. Zonal pricing is a form of “locational pricing” that would see the country divided into zones, in an effort to reduce grid constraints and energy costs.

In order to avoid any changes affecting the investment needed in new clean power capacity, the government pledges to “align” the process with the next CfD auction. It also flags the potential for “transitional or legacy arrangements” that could protect existing investments from future changes:

“We plan, therefore, to announce the final decisions on REMA and the timetable for their implementation, particularly in relation to wholesale market reform and any transitional or legacy arrangements, before the AR7 auctions open, giving investors clarity for prospective bids.”

Other actions include NESO promising an electricity system operability strategy for 2030, improved forecasting of medium to long-term grid operability needs and improved emissions reporting from NESO across all electricity markets.

To support greater flexibility in the electricity system, the government plans to publish a “low carbon flexibility roadmap” in 2025. This will consolidate existing and future actions to drive short and long-duration flexibility.

Currently, there is 4.5GW of battery storage in Great Britain, the majority of which is grid-scale assets. By 2030, 23-27GW of battery storage is expected to be needed to meet the demands of a clean power system.

The action plan includes specific measures to overcome “hurdles” in the rollout of battery storage, such as working with Ofgem to ease network connections. (See: Grid enhancement.)

It says it will bring in incremental market reforms to provide batteries and consumer-led flexibility with access to relevant markets. This could include, for example, households shifting demand from electric vehicle charging at home, to use abundant renewable generation late at night instead of during peak hours when the grid is strained.

To support this, the action plan suggests enhancing rewards for consumers who choose to participate in flexibility, as well as the need for changes to market access for flexibility providers and support for the rollout of smart appliances.

Figure X: Consumer-led flexibility at peak (GW), 2023-2030
Capacity of consumer-led flexibility needed from 2023 to 2030, divided by source. Source: Clean Power 2030 Action Plan, NESO.

Finally, work will be undertaken to enable portfolios of projects and activities to deliver consumer-led flexibility. Among other things, this builds on the rollout of the demand flexibility mechanism, whereby households are paid to reduce energy consumption during tight periods.

The action plan identifies the need for further long-duration flexibility technologies and announces support for the development of a hydrogen power business model to derisk investment and speed up the rate of deployment.

Additionally, Ofgem will introduce a “cap and floor scheme” to support investment in long-duration electricity storage. It says it is aiming to publish an open letter on specific aspects of the scheme soon, and in the first quarter of next year, DESNZ and Ofgem will publish the technical decisions undertaken to provide clarity on any outstanding areas of its design.

NESO has agreed to provide further advice as to the range of technologies needed. The scheme is expected to open to applications in the second quarter of next year.

Back to top

The post Analysis: How the UK plans to reach clean power by 2030 appeared first on Carbon Brief.

Analysis: How the UK plans to reach clean power by 2030

Continue Reading

Climate Change

Carbon Brief Quiz 2026: Picture Round 1 and 2

Published

on

All answers will need to be submitted via the Google form by the end of the half-time break

The post Carbon Brief Quiz 2026: Picture Round 1 and 2 appeared first on Carbon Brief.

Carbon Brief Quiz 2026: Picture Round 1 and 2

Continue Reading

Climate Change

Landmark deal to share Chile’s lithium windfall fractures Indigenous communities

Published

on

Rudecindo Espíndola’s family has been growing corn, figs and other crops for generations in the Soncor Valley in northern Chile, an oasis of green orchards in one of the driest places on Earth the Atacama desert.

Perched nearly 2,500 metres above sea level, his village, Toconao, means “lost corner” in the Kunza language of the Indigenous people who have lived and farmed the land in this remote spot for millennia.

“Our deep connection to this place is based on what we have inherited from our ancestors: our culture, our language,” said Espíndola, a member of a local research team that found evidence that people have inhabited the desert for more than 12,000 years.

This distant outpost is at the heart of the global rush for lithium, a silvery-white metal used to make batteries for electric vehicles (EV) and renewable energy storage that are vital to the world’s clean energy transition. The Atacama salt flat is home to about 25% of the world’s known lithium reserves, turning Chile into the world’s second-largest lithium producer after Australia.

For decades, the Atacama’s Indigenous Lickanantay people have protested against the expansion of the lithium industry, warning that the large evaporation ponds used to extract lithium from the brine beneath the salt flats are depleting scarce and sacred water supplies and destroying fragile desert ecosystems.

Espíndola joined the protests, fearing that competition for water could pose an existential threat to his community.

But last year, he was among dozens of Indigenous representatives who sat across the table from executives representing two Chilean mining giants to hammer out a governance model that gives Indigenous communities living close to lithium sites a bigger say over operations, and a greater share of the economic benefits.

A man wearing a black T-shirt and a hat stands in front of a tree
Rudecindo Espíndola stands in a green oasis near the village of Toconao in the Atacama desert (Photo: Francisco Parra)

A pioneering deal

The agreement is part of a landmark deal between state-owned copper miner Codelco and lithium producer the Sociedad Química y Minera de Chile (SQM) to extract lithium from the salt flats until 2060 through a joint venture called NovaAndino Litio.

The governance model that promises people living in Toconao and other villages around the salt flats millions of dollars in benefits and greater environmental oversight is the first of its kind in mineral-rich Chile, and has been hailed by industry experts as the start of a potential model for more responsible mining for energy transition metals.

NovaAndino told Climate Home News the negotiations with local communities represented an “unprecedented process that has allowed us to incorporate the territory’s vision early in the project’s design” and creates “a system of permanent engagement” with local communities.

The company added it will contribute to sustainable development in the area and help “the safeguarding of [the Lickanantay people’s] culture and environmental values”.

    For mining companies, such agreements could help reduce social conflicts and protests, which have delayed and stalled extraction in other parts of South America’s lithium-rich region, known as the lithium triangle.

    “Argentina and Bolivia could learn a lot from what we’re doing [here],” said Rodrigo Guerrero, a researcher at the Santiago-based Espacio Público think-tank, adding that adopting participatory frameworks early on could prevent them from “going through the entire cycle of disputes” that Chile has experienced.

    Justice at last?

    As part of the governance deal, NovaAndino has pledged to adopt technologies that will reduce water use and mitigate the environmental impacts of lithium extraction.

    It has also committed to hold more than 100 annual meetings with community representatives to build a “good faith” relationship, and an Indigenous Advisory Council will meet twice a year with the company’s sustainability committee to discuss its environmental strategy, company sources said. The meetings are due to begin next month.

    To oversee the agreement’s implementation, an assembly – composed of representatives from all 25 signatory communities – will track the project’s progress. In addition, NovaAndino will hold one-on-one meetings with each community to address issues such as the hiring of local people and the protection of Indigenous employees.

    A flamingo at the Chaxa Lagoon in the Atacama salt flat (Photo: REUTERS/Cristian Rudolffi)

    Espíndola said the deal, while far from perfect, was an important step forward.

    “Previously, Indigenous participation was ambiguous. Now we talk about participation at [every] hierarchical level of this process, a very strong empowerment for Indigenous communities,” said Espíndola, adding that it did not give local communities everything they had asked for. For instance, they will not hold veto power over NovaAndino’s decisions or have a formal shareholder role.

    But after years of conflict with mining companies, a form of “participatory justice is being done”, he said.

    Not everyone is convinced that the accord, pushed by Chile’s former leftist government, marks progress, however.

    “Not in our name”

    The negotiations have caused deep divisions among the Lickanantay, some of whom say greater engagement with mining companies will not stop irreparable damage to the salt flats on which their traditional way of life depends. Others fear the promise of more money will further erode community bonds.

    In January 2024, Indigenous communities from five villages closest to the mining operations, including Toconao, blocked the main access roads to the lithium extraction sites. They said the Council of Atacameño Peoples, which represents 18 Lickanantay communities and was leading discussions with the company, no longer spoke for them.

    Official transcripts of consultations on the extension of the lithium contracts and how to share the promised benefits reveal deep divisions. Tensions peaked when communities around the mining operations clashed over how to distribute the multimillion-dollar windfall, with villages closest to the mining sites demanding the largest share.

    Eventually, separate deals establishing a new governance framework over mining activities were reached between Codelco and SQM with 25 local communities, including a specific agreement for the five villages closest to the extraction sites.

    Codelco’s chairman Maximo Pacheco (Photo: REUTERS/Rodrigo Garrido)

    The division caused by the separate deal for the five villages “will cause historic damage” to the unity of the Atacama desert’s Indigenous peoples, said Hugo Flores, president of the Council of Atacameño Associations, a separate group representing farmers, herders and local workers who oppose the mining expansion.

    Sonia Ramos, 83, a renowned Lickanantay healer and well-known anti-mining activist, lamented the fracturing of social bonds over money, and for the sake of meeting government objectives.

    “There is fragmentation among the communities themselves. Everything has transformed into disequilibrium,” said the 83-year-old.

    “[NovaAndino] supposedly has economic significance for the country, but for us, it is the opposite,” she said.

    The company told Climate Home News it has “acted consistently” to promote “transparent, voluntary, and good-faith dialogue with the communities in the territory, recognising their diversity and autonomy, and always respecting their timelines and forms of participation”.

    A one-off deal or a model for others?

    The NovaAndino joint venture is a pillar of Chile’s strategy to double lithium production by 2031 and consolidate the copper-producing nation’s role in the clean energy transition as demand for battery minerals accelerates.

    Chile’s new far-right president, José Antonio Kast, who was sworn in last week, promised to respect the lithium contracts signed by his predecessor’s administration – including the governance model.

    Still, some experts say the splits over the new model highlight the need for legislation that mandates direct engagement and minimum community benefits for all large mining projects.

    “In the past, this has lent itself to clientelism, communities who negotiate best or arrive first get the better deal,” said Pedro Zapata, a programme officer in Chile for the Natural Resource Governance Institute.

    “This can be to the detriment of other communities with less strength. We cannot have first- and second-class citizens subject to the same industry,” he added.

    The government is already negotiating two more public-private partnerships to extract lithium with mining giant Rio Tinto, which it said would include a framework to engage with Indigenous communities and share some of the revenues. The details will need to be negotiated between local people, the government and the company.

    Sharing the benefits of mining

    Under the deal in the Atacama, NovaAndino will run SQM’s current lithium concessions until they expire in 2030 before seeking new permits to expand mining in the region under a vast project known as “Salar Futuro” – a process which will require further mandatory consultations with communities.

    Besides the participatory mechanism, the new agreement promises more money than ever before for salt flat communities.

    A stone arch welcomes visitors to the village of Peine, one of the closest settlements to lithium mining sites in the Atacama salt flat (Photo: REUTERS/Cristian Rudolffi)

    Depending on the global price of lithium and their proximity to the mining operations, Indigenous communities could collectively receive roughly $30 million annually in funding – about double what SQM currently disburses under existing contracts.

    When taking into account the company’s payments to local and regional authorities, contributions could reach $150 million annually, according to the government.

    To access these resources, each community will need to submit a pipeline of projects they would like funding for under a complex arrangement that includes five separate financial streams:

    • A general investment fund will distribute funding based on each village’s size and proximity to the mining sites
    • A development fund will support projects specifically in the five communities closest to the extraction sites
    • Contributions to farmers and livestock associations
    • Contributions to local governments
    • A groundbreaking “intergenerational fund” held in trust for the Lickanantay until 2060

    For many isolated communities in the Atacama desert, financial contributions from mining firms have funded essential public services, such as healthcare and facilities like football pitches and swimming pools.

    In the past, communities have used some of the benefits they received from mining to build their own environmental monitoring units, hiring teams of hydrogeologists and lawyers to scrutinise miners’ activities.

    Espíndola said the new model could pave the way for more ambitious development projects such as water treatment plants and community solar energy projects.

    A man in a white shirt and glasses stands in front of a stone wall
    Sergio Cubillos, president of the Peine community, was one of the Indigenous representatives in the negotiations with Codelco and SQM (Photo credit: Formando Rutas/ Daniela Carvajal)

    Competition for water

    The depletion of water resources is one of local people’s biggest environmental concerns.

    To extract lithium from the salt flats, miners pump lithium-rich brine accumulated over millions of years in underground reservoirs into gigantic pools, where the water is left to evaporate under the sun and leaves behind lithium carbonate.

    One study has shown that the practice is causing the salt flat to sink by up to two centimetres a year. SQM recently said its current operations consume approximately 11,500 to 12,500 litres of industrial freshwater for every metric ton of lithium produced.

    NovaAndino has committed to significantly reduce the company’s water use by returning at least 30% of the water it extracts from the brine and eliminating the use of all freshwater in its operations within five years of obtaining an environmental permit.

      Cristina Dorador, a microbiologist at the University of Antofagasta, told Climate Home News that reinjecting the water underground is untested at a large scale and could impact the chemical composition of the salt flats.

      Continuing to extract lithium from the flats until 2060 could be the “final blow” for this fragile ecosystem, she said.

      Asked to comment on such concerns, NovaAndino said any new technology will be “subject to the highest regulatory standards”, and pledged to ensure transparency through “an updated monitoring system with the participation of Indigenous communities”.

      High price for hard-won gains

      For the five communities living on the doorstep of the lithium pools, one of the biggest gains is being granted physical access to the mining sites to monitor the lithium extraction and its impact on the salt flats.

      That is a first and will strengthen communities’ ability to call out environmental harms, said Sergio Cubillos, the community president of Peine, the village closest to the evaporation ponds. It could also give them the means to seek remediation through the courts if necessary, Espíndola said.

      Gaining such rights represents long-overdue progress, Cubillos said, but it has come at a high price for the Lickanantay people.

      “Communities receiving money today is what has ultimately led to this division, because we haven’t been able to figure out what we want, how we want it, and how we envision our future as a people,” he said.

      Main image: A truck loads concentrated brine at SQM’s lithium mine at the Atacama salt flat in Chile (Photo: REUTERS/Ivan Alvarado)

      The post Landmark deal to share Chile’s lithium windfall fractures Indigenous communities appeared first on Climate Home News.

      Landmark deal to share Chile’s lithium windfall fractures Indigenous communities

      Continue Reading

      Climate Change

      Roadmap launched to restart deadlocked UN plastics treaty talks

      Published

      on

      Diplomats will hold a series of informal meetings this year in a bid to revive stalled talks over a global treaty to curb plastic pollution, before aiming to reconvene for the next round of official negotiations at the end of 2026 or early 2027.

      Hoping to find a long-awaited breakthrough in the deeply divided UN process, the chair of the talks, Chilean ambassador Julio Cordano, released a roadmap on Monday to inject momentum into the discussions after negotiations collapsed at a chaotic session in Geneva last August.

      Cordano wrote in a letter that countries would meet in Nairobi from June 30 to July 3 for informal discussions to review all the components of the negotiations, including thorny issues such as efforts to limit soaring plastic production.

        The gathering should result in the drafting of a new document laying the foundations of a future treaty text with options on elements with divergent views, but “no surprises” such as new ideas or compromise proposals. This plan aims to address the fact that countries left Geneva without a draft text to work on – something Cordano called a “significant limitation” in his letter.

        “Predictable pathway”

        The meeting in the Kenyan capital will follow a series of virtual consultations every four to six weeks, where heads of country delegations will exchange views on specific topics. A second in-person meeting aimed at finding solutions might take place in early October, depending on the availability of funding.

        Cordano said the roadmap should offer “a predictable pathway” in the lead-up to the next formal negotiating session, which is expected to take place over 10 days at the end of 2026 or early 2027. A host country has yet to be selected, but Climate Home News understands that Brazil, Azerbaijan or Kenya – the home of the UN Environment Programme – have been put forward as options.

        Countries have twice failed to agree on a global plastics treaty at what were meant to be final rounds of negotiations in December 2024 and August 2025.

        Divisions on plastic production

        One of the most divisive elements of the discussions remains what the pact should do about plastic production, which, according to the UN, is set to triple by 2060 without intervention.

        A majority, which includes most European, Latin American, African and Pacific island nations, wants to limit the manufacturing of plastic to “sustainable levels”. But large fossil fuel and petrochemical producers, led by Saudi Arabia, the United States, Russia and India, say the treaty should only focus on managing plastic waste.

        As nearly all plastic is made from planet-heating oil, gas and coal, the sector’s trajectory will have a significant impact on global efforts to reduce greenhouse gas emissions.

        Countries still far apart

        After an eight-month hiatus, informal discussions restarted in early March at an informal meeting of about 20 countries hosted by Japan.

        A participant told Climate Home News that, while the gathering had been helpful to test ideas, progress remained “challenging”, with national stances largely unchanged.

        The source added that countries would need to achieve a significant shift in positions in the coming months to make reconvening formal negotiations worthwhile.

        Deep divisions persist as plastics treaty talks restart at informal meeting

        Jacob Kean-Hammerson, global plastics policy lead at Greenpeace USA, said the new roadmap offers an opportunity for countries to “defend and protect the most critical provisions on the table”.

        He said that the document expected after the Nairobi meeting “must include and revisit proposals backed by a large number of countries, especially on plastic production, that have previously been disregarded”.

        “These measures are essential to addressing the crisis at its source and must be reinstated as a key part of the negotiations,” he added.

        The post Roadmap launched to restart deadlocked UN plastics treaty talks appeared first on Climate Home News.

        Roadmap launched to restart deadlocked UN plastics treaty talks

        Continue Reading

        Trending

        Copyright © 2022 BreakingClimateChange.com