Shortly after Memorial Day, the Georgia Public Service Commission (PSC) convened to hear testimony from parties asking for improvements in Georgia Power’s Integrated Resource Plan (IRP): the utility’s ten-year infrastructure plan for deciding what gets built, where electricity will flow, and who will pay for it. Multiple parties recommended improving system reliability and reducing costs through more comprehensive analysis of regional needs for transmission lines.

However, Commissioners and the utility were reluctant to move away from a traditional approach that relies heavily on Georgia Power building in-state power plants to meet the state’s growing energy needs. Like much of the Southeast, Georgia is experiencing new weather patterns, population growth, and the addition of major new individual electric loads on the system. These trends require a wide range of actions, including new and expanded transmission lines, in order to maintain reliable electric service.  Georgia Power’s ten-year plan includes billions of dollars of new in-state transmission lines to connect both new power plants and major new industries to the grid.  

The need for more energy will drive new transmission investments for Georgia Power, regardless of whether the utility chooses to build new power plants or increase connectivity to neighboring utilities. The status quo of Georgia Power’s closed transmission planning risks inefficient decisions showing up in your electric bill.

Improved Stakeholder Engagement, Role of Multi-Value Strategic Transmission

During the hearing, outside experts promoted the Carolinas Transmission Planning Collaborative as a successful model for stakeholder engagement that Georgia Power and its parent company, Southern, should follow when planning transmission locally through the Integrated Transmission System (ITS). Stakeholder meetings of the Carolinas Transmission Planning Collaborative, called the Transmission Advisory Group or TAG, are open to any individual or organization that signs up in advance. 

In contrast, Georgia’s ITS process all occurs between Georgia utilities behind closed doors. And while stakeholders can attend a separate southeast regional meeting (Southeast Regional Transmission Planning, often called “SERTP”) hosted by Southern with other utilities to discuss regional transmission planning across multiple companies, it merely conducts a limited number of studies and does not have direct input into Georgia Power’s local plans.

Additionally, Georgia Power’s process prioritizes using local transmission lines within a utility’s service area to maintain system reliability. While “keeping the lights on” is the paramount goal of utility operations, this approach ignores a wide array of other effects that the size and location of transmission lines have on the grid. These effects include which power plants are used the most often, the opportunity to use cheaper generation for the system, improved power flows during hours of high-electric demand, and the availability of assistance from neighboring utility systems if a local power plant fails.

All of these additional factors are evaluated in a more robust transmission process called “Multi-Value Strategic Transmission” (MVST). In 2023, Duke added an MVST process to the Carolinas Transmission Planning Collaborative, in response to direction from the North Carolina Utilities Commission. Duke acknowledged the value of MVST in their filing to the Federal Energy Regulatory Commission. “To be positioned to reliably address the many dynamic demands facing the transmission grid, including not just the generation transition, but greater electrification, increased electric vehicle adoption, and new economic development, including from prospective customers with significant energy demands to power data centers or manufacturing hubs, Duke Energy needs to evolve its planning process from siloed planning for reliability, economics, and public policy.” Duke’s first round of the MVST process is expected to conclude by the end of 2025.

Grid Strategies recently examined the value of building three regional lines across the Southeast using MVST. They found that if SERTP built three new regional transmission lines instead of local projects, the average residential customer would save $4.47 per year. That’s about half of what customers are paying for Georgia Power’s Vogtle Unit 4, which added about $8.95 to the average customer’s bill. For system planning, if the Georgia Public Service Commission ordered Southern Company and Georgia Power to consider regional transmission lines as least regret projects with multiple benefits, these savings to ratepayers would only increase.

Interregional Transfer Capability enhances Georgia’s grid when it is constrained

Despite indications that a more public process and more comprehensive analysis could save customers billions of dollars, some members of the Georgia Public Service Commission were concerned that reliance on neighboring systems would undermine reliability. Georgia’s state law for integrated resource planning, however, lists power purchases from neighboring states as one of six possible sources of supply of power. During Winter Storm Elliott, Georgia Power was able to keep the lights on only because of emergency purchases from Florida Power and Light to Southern. Without Florida’s support, Georgia Power would have seen outages. 

Congress also has tackled the issue of transmission lines needed for interregional coordination during severe weather.  A Congressionally-mandated November 2024 Interregional Transfer Capability Study found that current transfer capability between Southeastern utilities is insufficient during extreme weather. Additional reporting by Grid Strategies concluded that rising load growth will put additional strain on a local utilities’ generation, further increasing the need for transfer capability not only between southeastern utilities, but also with utilities in other regions, allowing a utility to receive power from a region not experiencing high demand at the same time.

During the IRP hearing, Georgia Power cited recent blackouts in Louisiana as an example of why transmission planning should remain a local, utility-by-utility process rather than be regionally coordinated. Louisiana is part of a regional transmission organization named MISO that stretches from the Gulf to Canada. But, in the words of New Orleans City Councilman JP Morrell, the lead regulator of the power company Entergy in the city of New Orleans, “If we had better transmission, we could have flowed power from other parts of the state and other parts of this nation to keep power on.” In this case, MISO had proposed improved transmission ties into southern Louisiana but state regulators didn’t approve the cost. When a nuclear power plant went down, transmission was inadequate to transfer power from elsewhere in the region.

Improved Engagement enhances Transparency and “Right-Sizing” the Investment 

As we outlined in our previous article, Georgia Power has the opportunity to improve its transmission planning by following our recommendations, which include: 

  1. Clearly marking which transmission projects support which electricity needs
  2. Waiting to approve new transmission projects until the associated load growth has reached key interconnection and construction milestones
  3. Planning for batteries and solar based on their real-world support of the grid

These recommendations would be further enhanced by Georgia Power adopting open engagement with stakeholders and looking at a broad array of benefits when upgrading the grid. Beginning these processes now for both local and regional transmission planning will save Georgia ratepayers money, support growing demand for electricity, and keep the lights on.

The post Transmission Major Topic at Georgia Power Hearing appeared first on SACE | Southern Alliance for Clean Energy.

Transmission Major Topic at Georgia Power Hearing

Continue Reading

Renewable Energy

Guiding America’s Future

Published

on

It’s easy to understand how Trump has great appeal to the hateful idiots and the amoral rich.

It’s much harder to see how it’s possible that a huge number of eligible voters are uninvolved in guiding the future of the United States, with many of them saying that “both sides are the same.”

Guiding America’s Future

Continue Reading

Renewable Energy

It’s PEOPLE Who Vote

Published

on

We often hear the MAGA folks claim that voting in the U.S. disproportionate favors the people in big cities, mostly along the coasts.

The obvious response: People vote, not acres of land.

And yes, it’s true that Trump has little appeal to the well-educated, highly productive people in Southern California, the Bay Area, the Mid-Atlantic, New England, other large cities like Chicago, Phoenix, Houston, and Seattle.

It’s PEOPLE Who Vote

Continue Reading

Renewable Energy

Global fleet, local knowledge: closing wind’s expertise gap

Published

on

Weather Guard Lightning Tech

Global fleet, local knowledge: closing wind’s expertise gap

This exclusive article originally appeared in PES Wind 3 – 2026 with the title, Global fleet, local knowledge: closing wind’s expertise gap. It was written by Allen Hall and other members of the Weather Guard Lightning Tech team.

As wind fleets expand across increasingly diverse operating environments, the expertise needed to solve their problems is becoming more dispersed. Closing the industry’s knowledge gap means connecting local challenges with specialist experience from across the global wind sector and beyond.

An operator finds something on a blade they have not seen before. Who do they call? The engineer who designed that blade moved on years ago. The service provider has not seen the problem either. Somewhere in the world, there’s probably a person who has spent 15 years working on precisely that failure mode. But there’s no reliable way to find them.

That scenario plays out again and again. It’s rare that a problem is unsolvable. A solution exists somewhere. The bigger problem is finding that solution, or the person close to solving it.

Wind has become a large, geographically dispersed industry with roughly 1.3 TW of installed capacity. The technical knowledge required to keep it running has dispersed with it. The knowledge is real, deep and often highly specialized, but it is scattered across the globe in small teams working in different markets.

This is not the first global industry to discover that no single organization can hold every discipline, and that different parts of the world present different problems.

Two answers, one problem

In January 2023, Andrew Billingsley took a call from Ørsted asking whether his company could recycle wind turbine blades. Billingsley is CEO of Plaswire, a polymer processor in Northern Ireland. It was not a wind company. Plaswire’s business had been built on finding a way to use plastics from aircraft seat manufacturing and other waste nobody else would handle: residue pulled out of biodigesters and municipal waste plants.

He said yes before he was certain the company could do it.

Plaswire had a proprietary process for combining polymers that materials engineers said couldn’t be combined. Ground blade fiber mixed well with the combined polymer. Plaswire says it now has capacity to process up to 11,000 tonnes of blades a year and has increased blade content in its product from ten percent to thirty percent. The company also reports that the resulting structural components can outperform the concrete and timber alternatives they replace.

The same waste stream produced an entirely different answer on the other side of the Atlantic. Everpoint Services in Houston, Texas decommissions wind and solar assets, leaving the company tasked with repurposing fiberglass blades. At a birthday party, Everpoint CEO Tyler Goodell put that problem to James Timmins, a drilling engineer who had spent his career planning and overseeing drilling operations for major oil companies.

Timmins realized that ground blade fiber might work as a fluid loss additive in oil, gas, and geothermal drilling, where fluid escaping into the formation can cost tens of thousands of dollars a day. Everpoint spent the next two years turning that idea into a product. The company says BladeBlok is patented and shipping globally from Houston.

Two regions, two answers, both effective. And in retrospect, it makes perfect sense. Northern Ireland has decades of depth in polymers and injection molding, so its answer was a polymer. Houston is a center of the global oil and gas industry, so its answer was drilling mud. Neither answer came out of the wind industry. Both came from regional industrial expertise meeting a problem that happened to land next to it.

Looking beyond Denmark

Modern wind turbine engineering grew up in Denmark, and in many ways it still lives there. The most prevalent turbine design was refined by Danish engineers. DTU Wind and Energy Systems still anchors much of the research on wind turbines. Ask a hard aerodynamic question today and there is a fair chance the answer comes from within Denmark.

What has changed is that designing turbines and operating them are different problems. They no longer happen in the same places. A machine is designed in a small number of locations. It is then operated wherever the wind blows: West Texas, Queensland, Gujarat, the North Sea, and the Spanish meseta.

The fleet is also getting older and more varied as it grows. Machines commissioned during the last boom are aging in ways nobody modeled, on sites with conditions nobody anticipated. That combination generates operational questions faster than any single organization can answer them. Those questions are local, specific, and urgent. Now, companies all over the world are being asked to solve wind’s problems with legacy knowledge, often from an adjacent industry, that originated a long way from where the turbine was built.

The same blade, four climates

The industry’s leading-edge erosion wisdom is shaped largely by northern European conditions. It is a real problem, well studied and well understood. It is also not the same problem in West Texas, where the air carries dust and insects, and where inspections routinely find turbines one to three years old that look as though they have run for far longer. Will Howell of Armour Edge describes one site near an open-cast mine where airborne marble particulates were destroying blades within two seasons.

India produces a variant that exists nowhere in Europe. During the northern dry season, a sticky, tar-like dirt builds on the blades until the flow separates and the blade effectively stalls. The monsoon washes it away. PowerCurve reports that the use of vortex generators in India has produced some of the largest energy gains it has recorded, exceeding five percent across a full year. India is now the fourth-largest wind market on earth, surpassing 56 GW; last year it added more capacity than Germany did.

Rosemary Barnes worked for a Danish blade manufacturer before returning to Australia in 2021 to work in operations. There, she found blades behaving unlike the ones she had known in Europe. The standard method of predicting erosion severity combines annual rainfall with tip speed. But when Barnes plotted Australian sites with known erosion problems against those two axes, she got a random scatter. The model had no predictive value in Australia.

Her firm, Pardalote Consulting, is now placing scientific-grade sensors in Australian wind farms to establish what actually drives erosion there. [Barnes is also a regular host of The Uptime Wind Energy Podcast.]

A library of experts

Today, finding the right specialist can be difficult.

After six years hosting the Uptime Wind Energy Podcast, I increasingly think of the podcast as a library. In the past year alone, we’ve highlighted solutions from companies in Latvia, Denmark, Northern Ireland, Spain, Australia, Scotland, and the United States. As an organizer of the Wind O&M Australia event, one of our goals has been to bring international expertise to the local market. And similarly, to allow the global market to learn from knowledge that has been internal to Australia.

The answers are out there

The wind industry does not have time to solve the same problem twice. Fleets are aging, budgets are tight, and a blade defect that sits unresolved for a season costs real production. The pressure is to move faster, and the fastest way to solve a problem is rarely on your own. The fastest way to solve a problem is to find the person who has solved it. That search has to be a global one. The specialist who understands your failure mode may be in Copenhagen, Riga, Edinburgh, or Houston, working for a company you have never heard of. Geography is not a reason to rule them out. Increasingly it is the reason to go looking. The Uptime Wind Energy Podcast has become one way of documenting that dispersed expertise, bringing together specialists working on specific problems across different markets.

wind turbines operate in a variety of climates facing a variety of problems

The answers are out there.

Unless otherwise noted, images here are from The Uptime Wind Energy Podcast.

Contact us for help understanding your lightning damage, future risks, and how to get more uptime from your equipment.

Download the full article from PES Wind here. Previous articles you may want to read:

Find a practical guide to solving lightning problems and filing better insurance claims here

See how a cohesive operational strategy can dramatically improve reliability and profitability

Global fleet, local knowledge: closing wind’s expertise gap

Continue Reading

Trending