Enlight Renewable Energy has closed financing for the energy storage portion of its Atrisco Solar and Energy Storage project, located outside Albuquerque, N.M.
Financing for the solar portion of the project closed last December.
The project, spread across 1,700 acres, contains 364 MW of solar generation capacity and 1.2 GWh of battery storage. Costing $827 million to build, it is set to be financed by $290 million of term debt and $420 million of tax equity, with Enlight’s long-term equity investment amounting to $117 million.
As part of the close, Enlight through its subsidiary, Clenera Holdings, entered into a loan agreement with a consortium of eight banks led by HSBC, totaling $401 million to finance project construction. The loan will convert into a $185 million term loan from the same group of lenders and tax equity financing of $222 million provided by U.S. Bancorp Impact Finance upon the project’s COD.
The term loan is structured with a 20-year underlying amortization profile with a five-year mini perm, and is subject to an all-in interest rate.
Tax equity was provided by Bank of America. The project’s tax equity financing qualified for the Energy Community IRA adder due to a brownfield addition to the project.
Project construction was led by RES, and the battery energy storage system provided by Tesla. Atrisco has signed a 20-year busbar PPA agreement with Public Service Company of New Mexico covering both electricity production and energy storage.
“The Atrisco complex is Enlight’s flagship project in the United States, and today’s financial close is another important step in the completion of this project,” says Gilad Yavetz, CEO of Enlight.
“We look forward to the phased COD of Atrisco, expected to begin during this quarter, in which years of effort will finally come to fruition. Enlight is embarking on an ambitious and rapid growth plan in the U.S., which is set to become a major market for us in the coming years, complementing the large and growing capacity footprint we have built up in MENA and Europe. Atrisco represents another step of this major expansion.”
The project is currently in the commissioning phase leading up to partial COD, and is expected to reach full COD later this year.
The post Enlight Closes on Atrisco Energy Storage Project appeared first on Solar Industry.
Renewable Energy
Joke on MAGA Attire
This is funny, but in actuality, sane people don’t physically attack the MAGA crowd; in fact, we don’t even make snide comments.
We keep our thoughts to ourselves. We may feel sorry for these people’s moral depravity and/or stupidity. We may be angry that the country that was once the envy of the world is now viewed with ridicule and disdain in its path to become irrelevant in global affairs.
But messing with hateful morons in red hats isn’t helping anyone.
Renewable Energy
Trump Campaigns for the Nobel Peace Prize
Here’s the latest on Trump’s efforts to be awarded the Nobel Peace Prize, while waging an aggressive war in Iran, executing people he suspects of carrying drug off the coast of Venezuela, pledging to take over Cuba, and annexing Greenland from a (former) ally.
Renewable Energy
Boycott Amazon
At left are a few good reasons not to shop from Amazon.
I use eBay, so as not to make this world an even worse place than it is now.
-
Greenhouse Gases9 months ago
Guest post: Why China is still building new coal – and when it might stop
-
Climate Change9 months ago
Guest post: Why China is still building new coal – and when it might stop
-
Greenhouse Gases2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Climate Change2 years ago
Bill Discounting Climate Change in Florida’s Energy Policy Awaits DeSantis’ Approval
-
Climate Change2 years ago嘉宾来稿:满足中国增长的用电需求 光伏加储能“比新建煤电更实惠”
-
Renewable Energy6 months agoSending Progressive Philanthropist George Soros to Prison?
-
Carbon Footprint2 years agoUS SEC’s Climate Disclosure Rules Spur Renewed Interest in Carbon Credits
-
Greenhouse Gases10 months ago
嘉宾来稿:探究火山喷发如何影响气候预测